Cumberland House Project
We continue to make progress at Cumberland House.
To date we have overseen the full erection of scaffold, the installation of 140 brand new windows across 32 of the 70 properties, cavity wall insulation to two faces of the building, the installation of new ventilation systems, complete with decorative boxing in works, to 42 of the 70 properties.
Pleasingly the removal of the existing EWI system is near full completion and we have started the installation of the new @SGWeberUK EWI system.